SAMPLE — redacted illustration. Project and names are fictional; the format, imagery, and method are real. Not a client report.

The sample packet

This is the report your owner opens every week.

Four pages, same shape, every delivery — flown, processed, and interpreted by a Part 107 team. Enter your email and we'll send this exact packet to your inbox. No demo. No login. No walkthrough.

Part 107-licensed pilots · per-flight COI · 24-hour turnaround · you own the imagery

Or scroll the full sample right now ↓
01 Executive brief The page your owner reads first — one minute, every week.
PAGE 01 EXECUTIVE BRIEF Week 14 · Monday, May 12, 2026

Maple Ridge Subdivision — Phase 2

Denver, CO · Prepared for: Midland Civil Contractors · Latus Report © 2026

What changed — observed in aerial capture

  • First units framing (NE corner): First-floor walls are up on the initial building pads. Lumber staged at each lot; framing crews were on site at capture observed.
  • Primary loop (front access): Aggregate base placed and compacted across the main loop. Curb and gutter poured along the east leg — forms stripped, no honeycombing in oblique imagery.
  • Staging yard (south laydown): Reorganized since last week — equipment consolidated and material stacked by trade. Clear haul path restored through the yard.
  • Stockpile (west corner): Drawn down from prior week. Material moved to the north pads for base course — confirm remaining quantity with the site team indicative.

What's likely next — based on construction sequence

  • Framing: Walls continue east; roof trusses expected as the first units close in expected.
  • Primary loop: Asphalt binder course once weather allows — 3 dry days in next-week forecast forecast.
  • Grading: Finish grading on the north pads ahead of the next foundation pour.

Risks to watch

  • HIGHWeather window for asphalt: Binder needs dry conditions. If rain arrives early, paving pushes and the loop stays on base for another week.
  • MEDStockpile draw-down: Remaining material looks light for the full base schedule — verify quantity before the next cut.
  • LOWFraming access: The south laydown is tight as lumber packages land. Clear haul path is holding, but it's worth watching.

Project status note

Coherent progress across the site since last capture: framing started, base down on the primary loop, and earthwork drawing toward finish grade. No change-order exposure is evident in the aerial record. Schedule position and sign-off status are not visible from the air — confirm with the site team for schedule and inspection updates.

Methods & sources

Observed = visually confirmed in orthomosaic, DSM, or oblique imagery from this week's capture. Indicative = derived from elevation models (±10–15%, not survey-grade — confirm with your surveyor). Expected = inferred from standard civil construction sequence — not from a project schedule. Forecast = from publicly available weather data, cited in report. This report is produced from weekly aerial capture processed locally with open-source photogrammetry and human analyst review. Quantities are indicative, derived from elevation models without ground control. No client activity log or schedule feed is used.

SAMPLE — FICTIONAL PROJECT
02 Annotated orthomosaic One stitched overhead with stable callouts — the map everyone points at.
PAGE 02 ANNOTATED ORTHOMOSAIC Week 14 · Maple Ridge Phase 2 · Denver, CO
Annotated orthomosaic of Maple Ridge Subdivision Phase 2, Week 14, with stable zone callouts, a north arrow, and a scale bar.

Full-site orthomosaic with zone callouts. Zone labels stay in the same place every week, so your team tracks a work front from first cut to final lift without relearning the map.

SAMPLE — FICTIONAL PROJECT
03 Change page Proof of movement — side by side, week over week, ready for pay apps.
PAGE 03 CHANGE PAGE Week 13 → Week 14 · Maple Ridge Phase 2

All quantities are indicative (±10–15%), derived from elevation models — not survey-grade. Confirm with your surveyor before use in pay apps.

Primary loop — base placed

PREVIOUS CAPTURE
Primary loop before aggregate base placement, Week 13.

Rough-graded loop. No base material placed.

THIS CAPTURE
Primary loop with aggregate base placed and compacted, Week 14.

Aggregate base compacted. Curb and gutter poured on the east leg observed.

Staging yard — reorganized

PREVIOUS CAPTURE
Staging yard before reorganization, Week 13.

Equipment and material spread across the yard. Haul path partially blocked.

THIS CAPTURE
Staging yard after reorganization with a clear haul path, Week 14.

Consolidated by trade. Clear haul path restored through the yard observed.

Stockpile — drawn down

PREVIOUS CAPTURE
Stockpile at full height, Week 13.

Full stockpile staged on the west corner.

THIS CAPTURE
Stockpile reduced after draw-down to the north pads, Week 14.

Reduced after draw-down. Volume change tracked from the elevation model indicative.

SAMPLE — FICTIONAL PROJECT
04 Curated media The shots that matter this week — captioned and chosen, not a folder dump.
PAGE 04 CURATED MEDIA Week 14 · 4 selected captures · Maple Ridge Phase 2
Wide overview of the full site, Week 14.

1. Full-site overview — all active fronts in one frame. Looking northwest.

First-floor framing underway on the northeast pads.

2. First units framing — walls up on the northeast pads. Lumber staged at each lot.

Framing progress on the east building pads.

3. Framing, east pads — progress advancing toward the interior lots.

Oblique orbit view of the site from the southeast corner.

4. Orbit view from the southeast — context for the owner and lender call.

SAMPLE — FICTIONAL PROJECT
+ Optional technical archive The elevation-model deliverables your VDC and engineering teams can dig into.
ARCHIVE TECHNICAL — OPTIONAL Delivered alongside the packet · Maple Ridge Phase 2
Slope classification map derived from the elevation model.

Slope classes. Derived from the elevation model — used to flag drainage and grading risk before it shows up as rework.

Cross sections showing cut and fill across the site.

Cross sections. Cut/fill profiles across the work fronts — indicative quantities for planning, not survey-grade.

SAMPLE — FICTIONAL PROJECT

Your site, in this format, every week